Planning Procedures¶
(1) NAWDEX Field Phase¶
- Flight Planning Phase:
- 12 September – 19 October 2016
- first possible flight: 19 Sep 2016 ** last possible flight: 16 Oct 2016
- Transfers:
- HALO: Thu, 15 September (to Keflavik) and Wed, 19 October (to OP)
- Falcon: Sat, 17 September (to Keflavik) and Wed, 19 October (to OP)
- Planning for the first days in Iceland
- Thu, 15 Sep: arrival of HALO and most of the flight planning and instrument teams
- Fri, 16 Sep: setup of the operation center and offices at the airport, flight planning with an announcement of first plans for Mon 19 Sep
- Sat, 17 Sep: potential day-off for HALO
- Sun, 18 Sep: kick-off-meeting (9-10 UTC)
- Mon, 19 Sep: first possible flight day
(2) Information Transfer ¶
- NAWDEX Campaign Wiki
- Information about daily schedule, flight plans, weather etc. is communicated via the NAWDEX Wiki
- The NAWDEX Wiki is editable by all participants (upon registration)
- The Wiki’s main page shows all essential information on: a Daily Schedule, the responsibilities, a planning summary matrix and instrument status
- All documents will be made available on the NAWDEX wiki page, daily reports are linked on separate campaign day pages: e.g. https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Daily_Report_2016_09_19
- The Wiki provides templates for all reports: https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Templates
- NAWDEX broadcasting via Adobe Connect
- Meetings will be available via live stream with the Adobe Connect System (Information will follow)
- It will not be possible of oral contributions for people outside Iceland. A real-time messaging will be available during the Meetings.
People from outside are welcome to send information to the Operation Center or a call during the day.
(3) Daily Schedule ¶
- General planning Meeting (every day at 11 UTC, 13 CEST) : max. 60 Min
- Aim: inform all participants about scientific plans and tentative flight plans, decide all open issues in coordination with the instrument groups and flight facility ** Structure: *** Key information from previous flight (2 minutes) *** Aircraft status report by FX-Operations *** Instrument status report by Instrument Manager *** Short weather summary: information about flight options for the next days and update for planning for the next day with the latest forecast *** Final discussion about flight pattern for next day (in case of 2 options) *** Announcement of tentative plans for Day+3 *** Coordination with other aircraft *** Demand of ground-based obs (organized by Ground-Based Observation coordinator) ** Presentation and discussion led by the Scientific Manager ** After the general meeting FX (pilots, operations) and the mission scientists work on filing flight plans