1 | 1 | Andreas Schäfler | h1. Planning Procedures |
---|---|---|---|
2 | 1 | Andreas Schäfler | |
3 | 1 | Andreas Schäfler | h2. (1) NAWDEX Field Phase |
4 | 1 | Andreas Schäfler | |
5 | 1 | Andreas Schäfler | * *Flight Planning Phase:* |
6 | 1 | Andreas Schäfler | |
7 | 1 | Andreas Schäfler | ** 12 September – 19 October 2016 |
8 | 1 | Andreas Schäfler | |
9 | 1 | Andreas Schäfler | ** first possible flight: 19 Sep 2016 |
10 | 1 | Andreas Schäfler | ** last possible flight: 16 Oct 2016 |
11 | 1 | Andreas Schäfler | |
12 | 1 | Andreas Schäfler | * *Transfers:* |
13 | 1 | Andreas Schäfler | |
14 | 1 | Andreas Schäfler | ** HALO: Thu, 15 September (to Keflavik) and Wed, 19 October (to OP) |
15 | 1 | Andreas Schäfler | |
16 | 1 | Andreas Schäfler | ** Falcon: Sat, 17 September (to Keflavik) and Wed, 19 October (to OP) |
17 | 1 | Andreas Schäfler | |
18 | 1 | Andreas Schäfler | * *Planning for the first days in Iceland* |
19 | 1 | Andreas Schäfler | |
20 | 2 | Andreas Schäfler | ** *Thu, 15 Sep*: arrival of HALO and most of the flight planning and instrument teams |
21 | 1 | Andreas Schäfler | |
22 | 2 | Andreas Schäfler | ** *Fri, 16 Sep*: setup of the operation center and offices at the airport, flight planning with an announcement of first plans for Mon 19 Sep |
23 | 1 | Andreas Schäfler | |
24 | 1 | Andreas Schäfler | ** *Sat, 17 Sep*: potential day-off for HALO |
25 | 1 | Andreas Schäfler | |
26 | 1 | Andreas Schäfler | ** *Sun, 18 Sep*: kick-off-meeting (9-10 UTC) |
27 | 1 | Andreas Schäfler | |
28 | 1 | Andreas Schäfler | ** *Mon, 19 Sep*: first possible flight day |
29 | 1 | Andreas Schäfler | |
30 | 1 | Andreas Schäfler | |
31 | 1 | Andreas Schäfler | h2. (2) Information Transfer |
32 | 2 | Andreas Schäfler | |
33 | 2 | Andreas Schäfler | * *NAWDEX Campaign Wiki* |
34 | 2 | Andreas Schäfler | |
35 | 3 | Andreas Schäfler | ** Information about daily schedule, flight plans, weather etc. is communicated via the NAWDEX Wiki |
36 | 2 | Andreas Schäfler | |
37 | 2 | Andreas Schäfler | ** The NAWDEX Wiki is editable by all participants (upon registration) |
38 | 2 | Andreas Schäfler | |
39 | 3 | Andreas Schäfler | ** The *Wiki’s main page* shows all essential information on: a Daily Schedule, the responsibilities, a planning summary matrix and instrument status |
40 | 2 | Andreas Schäfler | |
41 | 2 | Andreas Schäfler | ** All documents will be made available on the NAWDEX wiki page, daily reports are linked on separate campaign day pages: e.g. https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Daily_Report_2016_09_19 |
42 | 2 | Andreas Schäfler | |
43 | 2 | Andreas Schäfler | ** The Wiki provides *templates* for all reports: https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Templates |
44 | 1 | Andreas Schäfler | |
45 | 1 | Andreas Schäfler | * *NAWDEX broadcasting via Adobe Connect* |
46 | 1 | Andreas Schäfler | |
47 | 3 | Andreas Schäfler | ** Meetings will be available via live stream with the *Adobe Connect System (Information will follow)* |
48 | 2 | Andreas Schäfler | |
49 | 4 | Andreas Schäfler | ** It will not be possible of oral contributions for people outside Iceland. A real-time messe |
50 | 3 | Andreas Schäfler | |
51 | 3 | Andreas Schäfler | ** People that have comments from outside are welcome to send information to (needs to be decided, could be done by the technical manager (see description of responsibilities below) or a call to the operation center during the day. |
52 | 2 | Andreas Schäfler | |
53 | 2 | Andreas Schäfler | o REAL TIME MESSenging |
54 | 2 | Andreas Schäfler | |
55 | 2 | Andreas Schäfler | |
56 | 1 | Andreas Schäfler | |
57 | 1 | Andreas Schäfler | h2. (3) Daily Schedule |
58 | 1 | Andreas Schäfler | |
59 | 1 | Andreas Schäfler | h2. (4) Coordination with other Aircraft/Ground-Based Observation: |
60 | 1 | Andreas Schäfler | |
61 | 1 | Andreas Schäfler | h2. (5) Responsibilities |
62 | 1 | Andreas Schäfler | |
63 | 1 | Andreas Schäfler | h2. (6) Reports |