Planning Procedures¶
(1) NAWDEX Field Phase¶
- Flight Planning Phase: ** 12 September – 19 October 2016 ** first possible flight: 19 Sep 2016 ** last possible flight: 16 Oct 2016
- Transfers: ** HALO: Thu, 15 September (to Keflavik) and Wed, 19 October (to OP) ** Falcon: Sat, 17 September (to Keflavik) and Wed, 19 October (to OP)
- Planning for the first days in Iceland * *Thu, 15 Sep: arrival of HALO and most of the flight planning and instrument teams * *Fri, 16 Sep: setup of the operation center and offices at the airport, flight planning with an announcement of first plans for Mon 19 Sep * *Sat, 17 Sep: potential day-off for HALO * *Sun, 18 Sep: kick-off-meeting (9-10 UTC) * *Mon, 19 Sep: first possible flight day
(2) Information Transfer ¶
- NAWDEX Campaign Wiki ** Information about daily schedule, flight plans, weather etc. is communicated via the NAWDEX Wiki ** The NAWDEX Wiki is editable by all participants (upon registration) ** People that do not want to edit the page can send Information to a technical manager * The *Wiki’s main page shows all essential information on: a Daily Schedule, the responsibilities, a planning summary matrix and instrument status ** All documents will be made available on the NAWDEX wiki page, daily reports are linked on separate campaign day pages: e.g. https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Daily_Report_2016_09_19 * The Wiki provides *templates for all reports: https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Templates
- NAWDEX broadcasting via Adobe Connect
* Meetings will be available via live stream with the *Adobe Connect System (Information will follow)
** It will not be possible of oral contributions for people outside Iceland. A real-time messaging will be available during the Meetings.
People from outside are welcome to send information to the Operation Center or a call during the day.
(3) Daily Schedule ¶
- General planning Meeting (every day at 11 UTC, 13 CEST) : max. 60 Min
- Aim: inform all participants about scientific plans and tentative flight plans, decide all open issues in coordination with the instrument groups and flight facility ** Structure: *** Key information from previous flight (2 minutes) *** Aircraft status report by FX-Operations *** Instrument status report by Instrument Manager *** Short weather summary: information about flight options for the next days and update for planning for the next day with the latest forecast *** Final discussion about flight pattern for next day (in case of 2 options) *** Announcement of tentative plans for Day+3 *** Coordination with other aircraft *** Demand of ground-based obs (organized by Ground-Based Observation coordinator) ** Presentation and discussion led by the Scientific Manager ** After the general meeting FX (pilots, operations) and the mission scientists work on filing flight plans
- Flight planning meeting (every day at 17 UTC, 19 CEST)
- Aims: *** Wrap up of the discussion within the forecast team during the day *** Scientific discussion about options for the upcoming days, contribution by different groups *** Update of flight planning Matrix *** Presentation of tentative flight plans (to be filed in detail on next morning) *** Discussion about coordination of aircraft *** Decision on responsibilities ** Campaign steering Group must be present to decide on what plans will be priority for the next morning ** Presentation by chief forecaster supported by an assistant
- Quick-Look Meeting
- depending on the schedule quick-look Meetings will be held after the research flights and when instrument groups had enough time to prepare quicklooks ** after or before the flight planning meeting ** should be organized by the instrument manager (collect presentations)
- Debriefing
- Will be held after the research flights at the Airport *** Pilots and mission scientists
(4) Responsibilities¶
- HALO/Falcon Campaign Steering Group:
- Group of 5 people that reach a final decision if needed (in case of different opinions) ** Scientific Manager, Chief Forecaster, Instrument Manager, 2 NAWDEX Scientific steering group members
- Scientific Manager:
- central contact person that knows all about the planning activities of the upcoming days ** chairs the general planning meeting (presents weather summary, flight plans and science goals) ** guides the decision making process ** Deliverables: *** presentation at general meeting *** planning summary matrix (gives an overview of plans for upcoming days, see Wiki-page for an example) *** daily schedule (in coordination with DLR-FX operations) *** list of responsibilities on NAWDEX wiki page *** planning summary: a document that summarizes the planning process of the day and discussion at the meetings with focus on plans / changes / discussion Topics
- Chief Forecaster:
- coordinates the forecasting team: *** collects information from forecasting group *** provides information to scientific manager *** provides information to mission scientists *** chairs the Flight planning meeting ** Deliverables: *** Presentation at Flight planning meeting *** Weather Summary: document on the weather situation of the day, *** I would like to add an assistant position, a student that could prepare the Weather Summary
- Technical Manager:
- Organizes the meetings (on-time start, infrastructure (computer, video projector, streaming via Adobe Connect System) ** Takes care of NAWDEX wiki (updates of main page, presentations, summaries, pictures) ** Collects reports
- Instrument Manager:
- Collects information from all instrument PI’s on current isntrument status ** A person from the instrument groups ** Deliverables: *** Instrument summary (summary of the instrument status of the day, describe possible work on instruments) *** Instrument status table (overview of instrument status that is provided on the Wiki page)
- Mission Scientists
- 1-3 persons (1 per aircraft, 1 at the ground) that are responsible to conduct a mission ** Deliverables *** Pre-flight: Develop the flight plans with pilots and operations, define release locations for dropsondes, provide flight plan to technical manager for upload to Wiki-page *** Mission on-board: in-flight decisions HALO: communication with ground, dropsonde releases, Falcon: wind lidar operator *** Mission ground: monitors PLANET chat during the research flight, upload of most recent satellite images *** Post-flight: mission summary (document that summarizes all events during a flight including onboard/ground)
- Coordinator for Ground-Based Observations:
- Distributes information to all ground-based observation facilities * Activation of additional radiosonde observations *(more Information will follow)
- DLR Flight Facility: coordination of flights and flight planning with pilots
- Katrin Witte (Project engineer DLR-FX, katrin.witte[at]dlr.de) ** Andreas Minikin (Project engineer DLR-FX, andreas.minikin[at]dlr.de) ** Frank Probst (DLR-FX Operations, Frank.Probst[at]dlr.de) ** Stefan Hempe (DLR-FX Operations, Stefan.Hempe[at]dlr.de)
- Campaign Reporter:
- Creates the campaign diary that will be provided on the Wiki page ** Position can be filled by all volunteers: PhD student, instrument operator, radiosonde operator,… ** Deliverables: Create a short blog contribution that shows the day from different perspectives Collect some pictures of the day ** Here is an example that gives a rough idea http://blogs.esa.int/campaignearth/2015/05/20/windval-petta-reddast/
(5) Coordination with other Aircraft/Ground-Based Observation:¶
- French Falcon
- French Falcon obervation period: 29 Sep – 17 Oct *** Contacts: Julien Delanoe (LATMOS/IPSL/UVSQ), Gwendal Rivière (LMD-ENS), Philippe Arbogast (Météo France) *** The French planning team will stay with us in the operation center near the Airport * procedure on the exchange of information and regular meetings has to be discussed (should be done before the HALO/Falcon General Meeting starts) *** The Scientific Manager will be the contact person from our side
- Global Hawk / SHOUT
- Global Hawk: (Jim, please add exact dates with overlap), *** Contacts: Jim Doyle (NRL) will coordinate the exchange of information with the SHOUT team, Jason Dunion (NOAA) *** Daily coordination calls from XX Sep to XX Oct at XX UTC
- UK BAE 146
- Operates from Cranfield *** Operation period: 19-30 September, 9-16 October, 2-3 double-flight missions), *** Contact: John Methven (U Reading) *** Daily coordination calls from XX Sep to XX Oct at XX UTC
- Ground-based observations (this section needs to be specified)
- Managed by the ground-based observation coordinator ** Observations: *** DLR radiosondes (operated by M. Bramberger, from ) *** France: *** *Gwendal & Philippe please add information on possible contact persons for the Supersites *** Canada: ** automatic 6-hourly releases from 19 Sep - 17 Oct *** *(add list os Station names) *** UK: ** Contact: Geraint Vaughan *** *(add some Information on Aberystwyth super site) *** Norway: *** EUMETNET: in case of a positive vote for our proposal (decision expected for 1 Sep 2016) we will add the procedure for on-demand radiosondes within the European network