h1. NAWDEX 2016 Campaign (HALO & Falcon)

This is the official blog for the NAWDEX campaign, a webpage that can be edited by all NAWDEX team members that are registered. The aim is to inform all NAWDEX participants and interested colleagues about the campaign and to share the planning material. If you need information about the international NAWDEX Project please refer to http://nawdex.org/ and for the HALO/Falcon Project please refer to http://www.pa.op.dlr.de/nawdex/

In case you should have any questions please contact: *andreas.schaefler[at]dlr.de*

---

h2. NAWDEX daily campaign schedule

_[last change: 02 Oct, 2016, 09:03 UT]_

If not stated otherwise, all timings given below after September 18 are referring to UT, which is LT in Iceland.

---

h3. Sunday, Oct 02, 2016

*Aircraft schedule:*

* *DLR Falcon*
>05:45 --- Power on the aircraft
>07:15 --- *Pre-flight briefing in the hangar (go/no-go decision Falcon)*
>07:45 --- Power off
>07:50 --- Leave hangar / APU power
>08:20 --- *Take-Off* (approx. flight time: 3:30 h)
>11:50 --- ETA Keflavik
>
>_Flight crew:_
>_Philipp Weber, Stefan Grillenbeck, David Woudsma, Oliver Reitebuch, Oliver Lux_
>
>"Falcon flight plan":https://internal.wavestoweather.de/nawdex/attachments/download/281/D-CMET%20Map%20ATC%20NAWDEX%2028Sep2016.pdf
>
plan":https://internal.wavestoweather.de/nawdex/attachments/download/276/NAWDEX%20161002%20MAP%20DCMET_Update_.pdf

*%{color:green}Meeting times for entry into the airport at GOLDEN Gate%*
>
>%{color:green} **05:30** (Engelbert, Oliver, Oli, David); Gate -> Hangar: Engelbert%

>
>
*%{color:red}Meeting times for entry into the airport at SILVER Gate%*
>
>%{color:red} **06:45** (Philipp, Stefan G., Martin, Katrin, Frank); Gate -> Hangar: Frank%

>
* *DLR HALO*
> Flight cancelled due to repair

>
* *SAFIRE Falcon*
>08:30 --- *Take-Off* (approx. flight time: 3:30 h)
>12:00 --- ETA Keflavik
>
> second flight in the afternoon

---



h2. Responsibilities

| *Position* | *Name* | *Contact (Email*) | *mobile phone* |
| HALO/Falcon Campaign Steering Group:| X | X | X |
| Scientific Manager: | Jim Doyle | James.Doyle[at]nrlmry.navy.mil | X |
| Technical Manager: | X | X | X |
| Chief Forecaster: | Julian Quinting | julian.quinting[at]monash.edu | X |
| Instrument Manager: | Manuel Gutleben | manuel.gutleben[at]dlr.de | X |
| Coordinator Ground-Based Observations: | Jacob Maddison | j.maddison[at]pgr.reading.ac.uk | |
| Mission Scientist (D-CMET) 02. Oct| Oliver Reitebuch| oliver.reitebuch[at]dlr.de | +354 8667413 |
| Mission Scientist (D-ADLR) | | | X |
| Mission Scientist (ground) | | | X |
| DLR-FX Operations | Stefan Hempe| stefan.hempe[at]dlr.de | +49 172 20 00 688 |
| DLR-FX Project manager in Keflavik | Katrin Witte | katrin.witte[at]dlr.de | +49 172 741 3066 |


----

h2. Planning Summary Matrix (from 19 Sep 2016, 23:25 UTC)

----



h2. Instrument and Aircraft Status Matrix (from 1 Okt 2016, 12:00 UTC)

!{width:60%}NAWDEX_instrument_status_matrix_20161002.png!

----



h2. Observation Coordination Matrix( from XX Sep 2016, XX:XX UTC)

!{width:60%}NAWDEX_observation_coordination_matrix_2016XXXX.png!