Project

General

Profile

Planning Procedures » History » Version 2

Version 1 (Andreas Schäfler, 08/31/2016 10:56 AM) → Version 2/57 (Andreas Schäfler, 08/31/2016 11:03 AM)

h1. Planning Procedures

h2. (1) NAWDEX Field Phase

* *Flight Planning Phase:*

** 12 September – 19 October 2016

** first possible flight: 19 Sep 2016
** last possible flight: 16 Oct 2016

* *Transfers:*

** HALO: Thu, 15 September (to Keflavik) and Wed, 19 October (to OP)

** Falcon: Sat, 17 September (to Keflavik) and Wed, 19 October (to OP)

* *Planning for the first days in Iceland*

** *Thu, 15 Sep*: arrival of HALO and most of the flight planning and instrument
teams

** *Fri, 16 Sep*: setup of the operation center and offices at the airport, flight
planning with an announcement of first plans for Mon 19 Sep

** *Sat, 17 Sep*: potential day-off for HALO

** *Sun, 18 Sep*: kick-off-meeting (9-10 UTC)

** *Mon, 19 Sep*: first possible flight day

h2. (2) Information Transfer

* *NAWDEX Campaign Wiki*

** Information about daily schedule, flight plans, weather etc. is communicated via the NAWDEX wiki

** The NAWDEX Wiki is editable by all participants (upon registration)

** The *Wiki’s main page* shows all essential information on: Schedule, Responsibilities, Planning Summary Matrix and Instrument status

** All documents will be made available on the NAWDEX wiki page, daily reports are linked on separate campaign day pages: e.g. https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Daily_Report_2016_09_19

** The Wiki provides *templates* for all reports: https://internal.wavestoweather.de/nawdex/projects/nawdex/wiki/Templates

* *NAWDEX broadcasting via Adobe Connect*
** *Meetings will be available via live stream with the Adobe Connect System (Information will follow)

** *There won’t be the possibility of oral contributions via the Adobe System from people outside Iceland.

** *People that have comments from outside are welcome to send information to (needs to be decided, could be done by the technical manager (see description of responsibilities below) or a call to the operation center during the day.

o REAL TIME MESSenging



h2. (3) Daily Schedule

h2. (4) Coordination with other Aircraft/Ground-Based Observation:

h2. (5) Responsibilities

h2. (6) Reports