h1. Blog for the NAWDEX 2016 Campaign (HALO & Falcon)
2 2 Redmine Admin
3 72 Andreas Schäfler
This is the official blog for the NAWDEX campaign, a webpage that can be edited by all NAWDEX team members that are registered. The aim is to inform all NAWDEX participants and interested colleagues about the campaign and to share the planning material. If you need information about the international NAWDEX Project please refer to http://nawdex.org/ and for the HALO/Falcon Project please refer to http://www.pa.op.dlr.de/nawdex/
4 23 Andreas Schäfler
5 43 Andreas Schäfler
In case you should have any question before the campaign starts, please contact: *andreas.schaefler[at]dlr.de*
6 42 Andreas Schäfler
7 8 Andreas Schäfler
{{construction}}
8 6 Andreas Schäfler
9 29 Andreas Schäfler
10 18 Andreas Schäfler
----
11 29 Andreas Schäfler
12 18 Andreas Schäfler
13 31 Andreas Schäfler
14 31 Andreas Schäfler
15 31 Andreas Schäfler
16 56 Andreas Schäfler
h2. Schedule 
17 57 Andreas Schäfler
18 69 Andreas Schäfler
h3. For 12/13 September 2016 (all times are LT (UTC+2h))
19 58 Andreas Schäfler
20 66 Andreas Schäfler
* *Monday, Sept 12:*
21 1 Redmine Admin
22 1 Redmine Admin
  ** 10:00     Installation of specMACS in the boiler room (Tobi, DLR-FX)
23 71 Andreas Schäfler
24 70 Andreas Schäfler
  ** 10:30     Web conference - Planning Meeting
25 71 Andreas Schäfler
26 65 Andreas Schäfler
  ** 13:00     Installation of HAMP radiometer (Mario, DLR-FX)
27 1 Redmine Admin
28 64 Andreas Schäfler
* *Tuesday, Sept 13:*
29 62 Andreas Schäfler
30 65 Andreas Schäfler
  ** 08:00     Installation of HAMP radar (Lutz, Heike, DLR-FX)
31 71 Andreas Schäfler
32 70 Andreas Schäfler
  ** 10:30     Web conference - Planning Meeting
33 1 Redmine Admin
34 73 Andreas Minikin
* *Wednesday, Sept 14:*
35 73 Andreas Minikin
36 73 Andreas Minikin
  ** 08:00 ---     HALO on the ramp for aircraft tests (until approx. 12:00, power available if required)
37 73 Andreas Minikin
38 74 Andreas Minikin
  ** afternoon --- HALO trainings flight (required) (time tbd; duration ca. 30 min; instruments have to remain off)
39 73 Andreas Minikin
40 73 Andreas Minikin
* *Thursday, Sept 15:*
41 73 Andreas Minikin
42 73 Andreas Minikin
  ** ??:?? ---     Ferry flight planned (tbc)
43 73 Andreas Minikin
44 73 Andreas Minikin
45 55 Andreas Schäfler
h3. First days in Iceland:
46 68 Andreas Schäfler
47 55 Andreas Schäfler
* *Mon, 12 Sep:* beginning of the planning meetings (daily meetings at 8:30 UTC until Thu, 15 Sep, then 11 UTC from Iceland)
48 68 Andreas Schäfler
49 55 Andreas Schäfler
* *Thu, 15 Sep:* arrival of HALO and most of the flight planning and instrument teams 
50 68 Andreas Schäfler
51 1 Redmine Admin
* *Fri, 16 Sep:* setup of the operation center and offices at the airport, flight planning with an announcement of first plans for Mon 19 Sep
52 55 Andreas Schäfler
53 73 Andreas Minikin
* *Sat, 17 Sep:* potential day-off for HALO; arrival of Falcon
54 55 Andreas Schäfler
55 1 Redmine Admin
* *Sun, 18 Sep:* kick-off-meeting (9-10 UTC): information for all participants 
56 1 Redmine Admin
57 1 Redmine Admin
* *Mon, 19 Sep:* first possible flight day
58 1 Redmine Admin
59 1 Redmine Admin
.
60 1 Redmine Admin
.
61 1 Redmine Admin
.
62 1 Redmine Admin
63 1 Redmine Admin
----
64 1 Redmine Admin
65 1 Redmine Admin
h2. Responsibilities
66 1 Redmine Admin
67 73 Andreas Minikin
| *Position* | *Name* | *Contact (Email*) | *mobile phone* |
68 73 Andreas Minikin
| HALO/Falcon Campaign Steering Group:|  X | X | X |
69 73 Andreas Minikin
| Scientific Manager: | X |  X | X |
70 73 Andreas Minikin
| Technical Manager: | X |  X | X |
71 73 Andreas Minikin
| Chief Forecaster: | X |  X | X |
72 73 Andreas Minikin
| Instrument Manager: | X |  X | X |
73 73 Andreas Minikin
| Coordinator Ground-Based Observations: | X |  X | X |
74 73 Andreas Minikin
| Mission Scientist XX. Sep| X| X | X |
75 73 Andreas Minikin
| Mission Scientist XX. Sep| X| X | X |
76 73 Andreas Minikin
| DLR-FX Operations | X| X | X |
77 73 Andreas Minikin
| DLR-FX Project manager in Keflavik (until Sep 30) | Andreas Minikin | andreas.minikin@dlr.de | +49 174 951 1618 |
78 73 Andreas Minikin
| DLR-FX Project manager in Keflavik (from Sep 30) | Katrin Witte | katrin.witte@dlr.de | +49 172 741 3066 |
79 73 Andreas Minikin
 
80 50 Andreas Schäfler
81 11 Andreas Schäfler
----
82 1 Redmine Admin
83 47 Andreas Schäfler
h2. Planning Summary Matrix (from XX Sep 2016, XX:XX UTC)
84 46 Andreas Schäfler
85 44 Andreas Schäfler
!{width:60%}NAWDEX_planning_summary_matrix_2016XXXX.png!
86 22 Andreas Schäfler
87 1 Redmine Admin
----
88 1 Redmine Admin
89 47 Andreas Schäfler
h2. Instrument Status Matrix (from XX Sep 2016, XX:XX UTC)
90 1 Redmine Admin
91 45 Andreas Schäfler
!{width:60%}NAWDEX_instrument_status_matrix_2016XXXX.png!
92 46 Andreas Schäfler
93 45 Andreas Schäfler
----
94 45 Andreas Schäfler
95 47 Andreas Schäfler
h2. Observation Coordination Matrix( from XX Sep 2016, XX:XX UTC)
96 45 Andreas Schäfler
97 45 Andreas Schäfler
!{width:60%}NAWDEX_observation_coordination_matrix_2016XXXX.png!