1 | 92 | Redmine Admin | h1. NAWDEX 2016 Campaign (HALO & Falcon) |
---|---|---|---|
2 | 2 | Redmine Admin | |
3 | 72 | Andreas Schäfler | This is the official blog for the NAWDEX campaign, a webpage that can be edited by all NAWDEX team members that are registered. The aim is to inform all NAWDEX participants and interested colleagues about the campaign and to share the planning material. If you need information about the international NAWDEX Project please refer to http://nawdex.org/ and for the HALO/Falcon Project please refer to http://www.pa.op.dlr.de/nawdex/ |
4 | 23 | Andreas Schäfler | |
5 | 91 | Andreas Minikin | In case you should have any questions please contact: *andreas.schaefler[at]dlr.de* |
6 | 42 | Andreas Schäfler | |
7 | 91 | Andreas Minikin | --- |
8 | 1 | Redmine Admin | |
9 | 91 | Andreas Minikin | h2. NAWDEX daily campaign schedule |
10 | 1 | Redmine Admin | |
11 | 263 | Katrin Witte | _[last change: 06 Oct, 2016, 15:45 UT]_ |
12 | 1 | Redmine Admin | |
13 | 1 | Redmine Admin | If not stated otherwise, all timings given below after September 18 are referring to UT, which is LT in Iceland. |
14 | 262 | Katrin Witte | |
15 | 262 | Katrin Witte | --- |
16 | 262 | Katrin Witte | |
17 | 262 | Katrin Witte | h3. Friday, Oct 07, 2016 |
18 | 262 | Katrin Witte | |
19 | 262 | Katrin Witte | *Aircraft schedule:* |
20 | 262 | Katrin Witte | |
21 | 262 | Katrin Witte | * *DLR Falcon* |
22 | 262 | Katrin Witte | > |
23 | 262 | Katrin Witte | >11:55 --- Power on the aircraft |
24 | 262 | Katrin Witte | >14:55 --- Aushallen |
25 | 262 | Katrin Witte | >15:25 --- Take-Off (approx. Flight time 03:30h) |
26 | 262 | Katrin Witte | >19:00 --- Landing |
27 | 262 | Katrin Witte | > |
28 | 262 | Katrin Witte | >Scientific Flight Crew: B. Witschas, O. Lux |
29 | 262 | Katrin Witte | > |
30 | 262 | Katrin Witte | *%{color:green}Meeting times for entry into the airport at Silver Gate%* |
31 | 262 | Katrin Witte | > |
32 | 262 | Katrin Witte | > |
33 | 262 | Katrin Witte | >%{color:green} **11:40** D. Woudsma, B. Witschas, O. Lux, E. Nagel% |
34 | 262 | Katrin Witte | >%{color:green} **14:25** R. Welser, S. Grillenbeck, M. Zöger% |
35 | 262 | Katrin Witte | > |
36 | 262 | Katrin Witte | * *DLR HALO* |
37 | 262 | Katrin Witte | > |
38 | 262 | Katrin Witte | >09:45 --- Power on the aircraft |
39 | 262 | Katrin Witte | >12:00 --- Pushing HALO out of the Hangar |
40 | 262 | Katrin Witte | >12:00 --- Pre-Flight Briefing in the Hangar |
41 | 262 | Katrin Witte | >13:05 --- Take-Off (approx. flight time: 5:30) |
42 | 262 | Katrin Witte | >18:35 --- Landing |
43 | 262 | Katrin Witte | > |
44 | 262 | Katrin Witte | >Scientific Flight Crew: Mission-PI ?, F. Ewald, D. Hellmann, M. Gutleben, T. Koelling, M. Klingebiel |
45 | 262 | Katrin Witte | |
46 | 262 | Katrin Witte | *%{color:green}Meeting times for entry into the airport at Silver Gate%* |
47 | 262 | Katrin Witte | > |
48 | 262 | Katrin Witte | > |
49 | 262 | Katrin Witte | >%{color:green} **09:30** C. Grad, K. Witte, L. Hirsch, H. Konow, M. Jacob, M. Wirth, D. Ene% |
50 | 262 | Katrin Witte | >%{color:green} **11:05** T. Koelling, L. Höppler% |
51 | 263 | Katrin Witte | >%{color:green} **11:45** F. Ewald, D. Hellmann, M. Gutleben, M. Klingebiel, S. Gemsa, M. Grossrubatscher, T. Leder, C. Mallaun% |
52 | 1 | Redmine Admin | |
53 | 1 | Redmine Admin | --- |
54 | 255 | Katrin Witte | |
55 | 257 | Katrin Witte | h3. Thursday, Oct 06, 2016 |
56 | 255 | Katrin Witte | |
57 | 1 | Redmine Admin | *Aircraft schedule:* |
58 | 1 | Redmine Admin | |
59 | 255 | Katrin Witte | * *DLR Falcon* |
60 | 257 | Katrin Witte | >**no flight** |
61 | 257 | Katrin Witte | >No scientific work going on at the aircraft, just standard maintentance from DLR´s side. |
62 | 257 | Katrin Witte | > |
63 | 255 | Katrin Witte | * *DLR HALO* |
64 | 1 | Redmine Admin | > |
65 | 257 | Katrin Witte | >03:30 --- Power on the aircraft |
66 | 257 | Katrin Witte | >05:45 --- Pushing HALO out of the hangar, performing the aircraft test |
67 | 257 | Katrin Witte | >06:00 --- Pre-Flight Briefing in the hangar |
68 | 257 | Katrin Witte | >07:00 --- Take-Off (approx. flight time: 8:30) |
69 | 257 | Katrin Witte | >15:30 --- Landing |
70 | 1 | Redmine Admin | > |
71 | 257 | Katrin Witte | >Scientific Flight Crew: M. Bramberger (PI), S. Groß, H. Konow, M. Jacob, M. Gutleben, K. Wolf |
72 | 257 | Katrin Witte | |
73 | 257 | Katrin Witte | *%{color:green}Meeting times for entry into the airport at Golden Gate%* |
74 | 257 | Katrin Witte | > |
75 | 257 | Katrin Witte | > |
76 | 257 | Katrin Witte | >%{color:green} **02:45** C. Grad, K. Witte, M. Klingebiel, D. Hellmann, L. Hirsch, M. Wirth, D. Ene% |
77 | 257 | Katrin Witte | >%{color:green} **04:30** T. Koelling, L. Höppler% |
78 | 258 | Katrin Witte | >%{color:green} **05:00** R. Welser, S. Gemsa, T. Leder, C. Mallaun, S. Hempe, S. Storhas% |
79 | 257 | Katrin Witte | >%{color:green} **05:30** M. Bramberger, S. Groß, H. Konow, J. Jacob, M. Gutleben, K. Wolf, T. Carlsen% |
80 | 257 | Katrin Witte | |
81 | 255 | Katrin Witte | --- |
82 | 255 | Katrin Witte | |
83 | 257 | Katrin Witte | h3. Wednesday, Oct 05, 2016 |
84 | 255 | Katrin Witte | |
85 | 255 | Katrin Witte | *Aircraft schedule:* |
86 | 255 | Katrin Witte | |
87 | 255 | Katrin Witte | * *DLR Falcon* |
88 | 257 | Katrin Witte | >*Day-Off today* |
89 | 255 | Katrin Witte | > |
90 | 257 | Katrin Witte | * *DLR HALO* |
91 | 255 | Katrin Witte | > |
92 | 257 | Katrin Witte | >Technical problem is solved. Test inside the Hangar was successful. |
93 | 257 | Katrin Witte | >Test outside on the Apron is officially required before the next flight. |
94 | 257 | Katrin Witte | >No flight today. |
95 | 255 | Katrin Witte | > |
96 | 249 | Katrin Witte | --- |
97 | 249 | Katrin Witte | |
98 | 249 | Katrin Witte | h3. Tuesday, Oct 04, 2016 |
99 | 249 | Katrin Witte | |
100 | 249 | Katrin Witte | *Aircraft schedule:* |
101 | 1 | Redmine Admin | |
102 | 251 | Katrin Witte | * *DLR Falcon* |
103 | 249 | Katrin Witte | >*2 Flights planned for Tuesday* |
104 | 250 | Katrin Witte | > |
105 | 250 | Katrin Witte | >05:00 --- Power on the aircraft |
106 | 249 | Katrin Witte | >07:00 --- Pulling the aircraft out of Hangar, Fueling |
107 | 249 | Katrin Witte | >08:00 --- Take-Off (approx. flight time: 3:30h) |
108 | 1 | Redmine Admin | >11:30 --- Landing |
109 | 251 | Katrin Witte | > |
110 | 251 | Katrin Witte | >12:00 --- Fueling |
111 | 251 | Katrin Witte | >13:10 --- Take-Off (approx. flight time: 2:30h) |
112 | 251 | Katrin Witte | >15:40 --- Landing |
113 | 249 | Katrin Witte | > |
114 | 249 | Katrin Witte | >Flight Crew: Philipp Weber, Stefan Grillenbeck, David Woudsma, Benjamin Witschas, Oliver Lux |
115 | 249 | Katrin Witte | > |
116 | 1 | Redmine Admin | > |
117 | 1 | Redmine Admin | *%{color:green}Meeting times for entry into the airport at Golden Gate%* |
118 | 1 | Redmine Admin | > |
119 | 1 | Redmine Admin | > |
120 | 1 | Redmine Admin | >%{color:green} **04:30** (Engelbert, Oliver, Olli, Benny, David); Gate -> Hangar: Engelbert, Olli% |
121 | 1 | Redmine Admin | *%{color:red}Meeting times for entry into the airport at Silver Gate%* |
122 | 1 | Redmine Admin | > |
123 | 1 | Redmine Admin | > |
124 | 1 | Redmine Admin | >%{color:red} **07:00** (Stefan Grillenbeck, Philipp Weber); Gate -> Hangar: Katrin/Stefan% |
125 | 1 | Redmine Admin | > |
126 | 1 | Redmine Admin | > |
127 | 1 | Redmine Admin | > |
128 | 1 | Redmine Admin | > |
129 | 1 | Redmine Admin | * *DLR HALO* |
130 | 1 | Redmine Admin | > |
131 | 1 | Redmine Admin | >Due to a technical problem with the aircraft, today´s flight had to be cancelled. |
132 | 1 | Redmine Admin | >There will definitely be no HALO flight today. |
133 | 1 | Redmine Admin | >We had to order a spare part and hope to get it to Keflavik tomorrow. |
134 | 1 | Redmine Admin | > |
135 | 257 | Katrin Witte | --- |
136 | 257 | Katrin Witte | |
137 | 257 | Katrin Witte | h3. Monday, Oct 03, 2016 |
138 | 257 | Katrin Witte | |
139 | 257 | Katrin Witte | *Aircraft schedule:* |
140 | 257 | Katrin Witte | |
141 | 257 | Katrin Witte | * *DLR Falcon* |
142 | 257 | Katrin Witte | >**no flight** |
143 | 257 | Katrin Witte | > |
144 | 257 | Katrin Witte | >09:00 - 16:00 --- Power on the aircraft |
145 | 257 | Katrin Witte | > |
146 | 257 | Katrin Witte | *%{color:green}Meeting times for entry into the airport at Silver Gate%* |
147 | 257 | Katrin Witte | > |
148 | 257 | Katrin Witte | > |
149 | 257 | Katrin Witte | >%{color:green} **08:30** (Engelbert, Oliver, Olli, Benny, Stephan, David); Gate -> Hangar: Engelbert, Olli% |
150 | 257 | Katrin Witte | > |
151 | 257 | Katrin Witte | * *DLR HALO* |
152 | 257 | Katrin Witte | > tbd (due to repair) |
153 | 257 | Katrin Witte | |
154 | 203 | Frank Probst | --- |
155 | 242 | Katrin Witte | |
156 | 242 | Katrin Witte | h3. Monday, Oct 03, 2016 |
157 | 242 | Katrin Witte | |
158 | 242 | Katrin Witte | *Aircraft schedule:* |
159 | 242 | Katrin Witte | |
160 | 242 | Katrin Witte | * *DLR Falcon* |
161 | 242 | Katrin Witte | >**no flight** |
162 | 242 | Katrin Witte | > |
163 | 242 | Katrin Witte | >09:00 - 16:00 --- Power on the aircraft |
164 | 242 | Katrin Witte | > |
165 | 242 | Katrin Witte | *%{color:green}Meeting times for entry into the airport at Silver Gate%* |
166 | 242 | Katrin Witte | > |
167 | 244 | Katrin Witte | > |
168 | 242 | Katrin Witte | >%{color:green} **08:30** (Engelbert, Oliver, Olli, Benny, Stephan, David); Gate -> Hangar: Engelbert, Olli% |
169 | 242 | Katrin Witte | > |
170 | 242 | Katrin Witte | * *DLR HALO* |
171 | 242 | Katrin Witte | > tbd (due to repair) |
172 | 242 | Katrin Witte | |
173 | 242 | Katrin Witte | --- |
174 | 73 | Andreas Minikin | |
175 | 73 | Andreas Minikin | h2. Responsibilities |
176 | 73 | Andreas Minikin | |
177 | 100 | Christian Grams | | *Position* | *Name* | *Contact (Email*) | *mobile phone* | |
178 | 166 | Heini Wernli | | HALO/Falcon Campaign Steering Group:| X | X | X | |
179 | 260 | Julian Quinting | | Scientific Manager: | John Methven | j.methven[at]reading.ac.uk | X | |
180 | 157 | Heini Wernli | | Technical Manager: | X | X | X | |
181 | 260 | Julian Quinting | | Chief Forecaster: | Bas Crezee | sebastiaan.crezee[at]env.ethz.ch | X | |
182 | 202 | Leo Saffin | | Instrument Manager: | Manuel Gutleben | manuel.gutleben[at]dlr.de | X | |
183 | 223 | Frank Probst | | Coordinator Ground-Based Observations: | Jacob Maddison | j.maddison[at]pgr.reading.ac.uk | | |
184 | 259 | Oliver Lux | | Mission Scientist (D-CMET) | Benjamin Witschas| benjamin.witschas[at]dlr.de | +354 8668270 | |
185 | 260 | Julian Quinting | | Mission Scientist (D-ADLR) | Martina Bramberger | martina.bramberger[at]dlr.de | X | |
186 | 261 | Julian Quinting | | Mission Scientist (ground) | Julian Quinting | julian.quinting[at]monash.edu | X | |
187 | 235 | Frank Probst | | DLR-FX Operations | Stefan Hempe| stefan.hempe[at]dlr.de | +49 172 20 00 688 | |
188 | 11 | Andreas Schäfler | | DLR-FX Project manager in Keflavik | Katrin Witte | katrin.witte[at]dlr.de | +49 172 741 3066 | |
189 | 1 | Redmine Admin | |
190 | 47 | Andreas Schäfler | |
191 | 101 | Christian Grams | ---- |
192 | 44 | Andreas Schäfler | |
193 | 101 | Christian Grams | h2. Planning Summary Matrix (from 19 Sep 2016, 23:25 UTC) |
194 | 123 | Christian Grams | |
195 | 1 | Redmine Admin | |
196 | 47 | Andreas Schäfler | |
197 | 112 | Manuel Gutleben | ---- |
198 | 254 | Manuel Gutleben | |
199 | 106 | Manuel Gutleben | h2. Instrument and Aircraft Status Matrix (from 5 Okt 2016, 09:00 UTC) |
200 | 254 | Manuel Gutleben | |
201 | 45 | Andreas Schäfler | !{width:60%}NAWDEX_instrument_status_matrix_20161005.png! |
202 | 47 | Andreas Schäfler | |
203 | 45 | Andreas Schäfler | ---- |
204 | 45 | Andreas Schäfler | |
205 | 1 | Redmine Admin | h2. Observation Coordination Matrix( from XX Sep 2016, XX:XX UTC) |
206 | 1 | Redmine Admin | |
207 | 1 | Redmine Admin | !{width:60%}NAWDEX_observation_coordination_matrix_2016XXXX.png! |