NAWDEX 2016 Campaign (HALO & Falcon)¶
This is the official blog for the NAWDEX campaign, a webpage that can be edited by all NAWDEX team members that are registered. The aim is to inform all NAWDEX participants and interested colleagues about the campaign and to share the planning material. If you need information about the international NAWDEX Project please refer to http://nawdex.org/ and for the HALO/Falcon Project please refer to http://www.pa.op.dlr.de/nawdex/
In case you should have any questions please contact: andreas.schaefler[at]dlr.de
NAWDEX daily campaign schedule¶
[last change: 09 Oct, 2016, 14:30 UT]
If not stated otherwise, all timings given below after September 18 are referring to UT, which is LT in Iceland.
Monday, Oct 10, 2016¶
Aircraft schedule:
- DLR Falcon
No flight!
- DLR HALO
08:45 --- Power on the aircraft
11:00 --- Pushing the aircraft out of the Hangar, Scientific briefing in the hangar
12:00 --- Take-off (approx. flight time: 07:30h)
19:30 --- Landing
Scientific Crew: J. Mack(Mission-PI), M. Gutleben, M. Klingebiel, B. Brügmann, K. Wolf, M. Bramberger
Meeting times for entry into the airport at Silver Gate
08:15 C. Grad, K. Witte, L. Hirsch, T. Carlsen, M. Wirth, D. Ene, M. Jacob, H. Konow ; Shuttle from Gate to Terminal: Katrin
10:00 T. Koelling, L. Höppler, M. Bramberger, M. Klingebiel, B. Brügmann, S. Storhas; Shuttle from Gate to Terminal: Stephan, Katrin
10:45 S. Gemsa, M. Grossrubatscher, T. Leder, C. Mallaun, S. Hempe, J. Mack, M. Gutleben, K. Wolf; Shuttle from Gate to Terminal: Christian, Katrin
Sunday, Oct 09, 2016¶
Aircraft schedule:
- DLR Falcon
11:45 --- Power on the aircraft
14:45 --- Pulling the aircraft out of the hangar
15:20 --- Take-off (approx. flight time: 02:55h)
18:15 --- Landing
Scientific Crew: B. Witschas, O. Lux
Meeting times for entry into the airport at Silver Gate
11:30 D. Woudsma, B. Witschas, C. Lemmerz, O. Lux, E. Nagel
- DLR HALO
06:45 --- Power on the aircraft
09:00 --- Pushing the aircraft out of the Hangar, Scientific briefing in the hangar
10:05 --- Take-off (approx. flight time: 08:35h)
18:40 --- Landing
Scientific Crew: M. Böttcher (Mission-PI), A. Schäfler, M. Gutleben, T. Koelling, F. Ewald, S. Groß
Meeting times for entry into the airport at Silver Gate
06:20 C. Grad, K. Witte, L. Hirsch, H. Konow, M. Wirth, D. Ene, S. Groß; Shuttle from Gate to Terminal: Katrin
08:00 T. Koelling, L. Höppler, S. Storhas, M. Zöger, K. Wolf, T. Carlsen; Shuttle from Gate to Terminal: Stephan, Katrin
08:45 S. Gemsa, M. Grossrubatscher, T. Leder, C. Mallaun, S. Hempe, F. Ewald, M. Gutleben, S. Groß, M. Böttcher, A. Schäfler; Shuttle from Gate to Terminal: Christian, Katrin
Saturday, Oct 08, 2016¶
Aircraft schedule:
- DLR Falcon
No flight.
Day-off for the Falco Crew.
- DLR HALO
No flight.
Day-off for the HALO Crew.
Friday, Oct 07, 2016¶
Aircraft schedule:
- DLR Falcon
Due to the weather conditions, the flight for today got cancelled.
- DLR HALO
Due to the weather conditions, the flight for today got cancelled.
Responsibilities¶
Position | Name | Contact (Email) | mobile phone |
HALO/Falcon Campaign Steering Group: | X | X | X |
Scientific Manager: | John Methven | j.methven[at]reading.ac.uk | X |
Technical Manager: | X | X | X |
Chief Forecaster: | Matthias Roethlisberger | matthias.roethlisberger[at]giub.unibe.ch | X |
Instrument Manager: | Manuel Gutleben | manuel.gutleben[at]dlr.de | X |
Coordinator Ground-Based Observations: | Lucas Hoeppler | lucas.hoeppler[at]physik.uni-muenchen.de | X |
Mission Scientist (D-CMET) | Benjamin Witschas | benjamin.witschas[at]dlr.de | +354 8668270 |
Mission Scientist (D-ADLR) | Maxi Boettcher | maxi.boettcher[at]env.ethz.ch | X |
Mission Scientist (ground) | Tobias Selz | tobias.selz[at]lmu.de | X |
DLR-FX Operations | Stefan Hempe | stefan.hempe[at]dlr.de | +49 172 20 00 688 |
DLR-FX Project manager in Keflavik | Katrin Witte | katrin.witte[at]dlr.de | +49 172 741 3066 |